Thursday, September 26, 2024

Seasonal Road Maintenance - Final stages for 2024


Peers, the contractor is back on the mountain and working to complete the seasonal work.    Please use extra caution on the roads, and plan a few extra minutes into your trips.  

Planned work.  

  • Touch-up grading on the major roads including Storm Mtn Drive up to the Hi/Low 

  • Mag-chloride application on the trouble areas and high-volume roads 

  • Placement of additional recycled asphalt base on the Access Road 

  • Final Grade and Mag-chloride application on the access road.  

 

The schedule is weather and resource dependent, we will attempt to let folks know as best possible the days where mag-chloride will be applied. 

 

Thanks,  

 

Storm Mountain PID
stormmountainpid@gmail.com

Final Roadwork for the Season

Foster Dirt will be completing the seasonal work by the end of next week .         Remaining items:    Additional  grading above the High/Lo...