Thursday, August 18, 2022

Heavy Rains & Culverts

Hello Storm Mountain,

With the heavy rains this last week, please consider checking that the culvert on your private driveway is draining properly. The culverts can get clogged very quickly in the heavy rains and diverting water from the public right of way saves us all money. Reach out to the PID if you need assistance cleaning your culvert and we’ll see if we can connect you with a volunteer willing to help. 

Thank you!
Connie Garrett
Secretary, Storm Mountain PID #55
stormmountainpid@gmail.com
970-429-5350

Friday, August 5, 2022

Road Work Update for August

Hello Storm Mountain, 


The contractor has completed grading and ditching in the lower filings.  We have a lot of work scheduled in August, so expect to see the crew working around the mountain.  The scheduled work is detailed below and will adjust based on weather and availability of materials.


August 8-12

  • Grade the upper filings
  • Put road base on trouble areas
  • Patch chip seal on the Access Road
  • Trim trees back from public right of way


August 15-19

  • Continue grading and ditching in upper filings
  • Continue to spread and compact road base in trouble areas
  • Clean culverts

Mag chloride will be applied from Lakeview to Snow Top/Palisade intersection later in the season, and we will share specific dates when we have it. Please drive cautiously around work crews, and allow yourself extra time to get to your destination safely.


Have an excellent weekend!

Connie Garrett 

Secretary

Storm Mountain PID #55

stormmountainpid@gmail.com

970-429-5350

Monday Road Conditions - March 18, 2024

  Community,    A big thank you to all the volunteers who worked throughout this storm event to improve the road conditions for everyone.  A...